The claim was served.
Now every clock is running.

Security of payment legislation runs on business days, and business days are not what most people assume. Enter the date the payment claim was served and see the deadlines that follow in your jurisdiction.

Business days are not calendar days, and they are not the same in every state.

Queensland and Victoria both exclude the period from 22 December to 10 January from the definition of a business day. The other jurisdictions do not. Public holidays differ by state. A deadline counted the obvious way is frequently wrong, and being wrong by one day is the same as being wrong by a month.

Your contract can shorten these periods but it cannot extend them. The statutory timeframes for payment schedules and due dates are drafted as "the earlier of the period in the contract or X business days" — so a contract specifying five days operates, and one specifying thirty does not. Attempting to contract out of the Act is void. Adjudication windows are fixed by statute and cannot be varied by agreement at all.

The Claim

Where the construction work was carried out.
The date it was actually received by the respondent, not the date on the invoice.
Affects the due date for payment in several jurisdictions.
Periods stated in your contract — optional
Business days. Leave blank if the contract is silent. The Act applies the earlier of the contract period or the statutory one — so a shorter period in your contract operates, and a longer one does not.
Business days after the claim is served. The Act sets a maximum; a contract may specify an earlier date but cannot extend it.

Nothing you enter is sent anywhere. The calculation runs in your browser and nothing is stored or transmitted.

Applicable Legislation

Select a jurisdiction and enter the date the payment claim was served.

The statute sets the floor. Your contract sets the trap.

Most of these periods can be shortened by the contract, and a contractual notice regime sitting alongside the statutory one can extinguish an entitlement long before any of these deadlines arrive. Contract Risk Intelligence reads the contract and tells you which clauses carry that weight, what they do to you, and what position to take before you sign. Transparent pricing. No demo required.

See pricing
Clause-by-clause review from L1
🔒

Nothing is collected

No sign-up, no email, no tracking of what you enter. The calculation runs in your browser.

📅

Indicative only

Dates are a guide. Check them against the legislation and your contract before you rely on any of them.

⚖️

Not legal advice

This tool counts business days. It does not assess whether your claim is valid or your entitlement is made out.

Commercial intelligence only. Not legal advice. This calculator counts business days from a date you supply and produces indicative dates only. It does not interpret your contract, assess the validity of a payment claim, determine whether an entitlement exists, or account for every circumstance that may affect a statutory period. Business day definitions, public holidays and statutory periods change. Verify every date against the current legislation and your contract, and obtain advice from a qualified construction lawyer before acting. PiVOTiQ Commercial Intelligence, its directors, employees and agents exclude all liability, whether in contract, tort (including negligence), for breach of statutory duty, or otherwise, for any loss, damage, cost or expense of any kind arising directly or indirectly from reliance on any output, to the maximum extent permitted by applicable law including the Australian Consumer Law. PiVOTiQ Commercial Intelligence | ABN 90 666 355 666 | www.pivotiq.com.au